Gold Line Bridge Almost Done

Gold Line spokesman Habib Balian writes:

"The Gold Line Bridge Construction will be complete in just one month. The Construction Authority and Skanska are focusing on final bridge details including the basket reeds, barrier and retaining walls, lighting and landscaping. Overall, the bridge is coming together as envisioned and will only be enhanced by the completion of these final details....

"As mentioned previously, another significant project element is the $160 million Gold Line Operations Campus in Monrovia being built to accommodate Metro's light rail vehicle fleet. With demolition now complete at the 24-acre site and grading underway, FTC crews are focused on completing the material removal, relocating utilities, and preparing to mass grade the largest single project element of the Foothill Extension project."

- Brad Haugaard