The Gold Line reports that the Santa Anita freeway bridge is on schedule, and that ...
during the coming months, crews will install the temporary support structure called falsework over the eastbound lanes of the I-210 Freeway. For safety purposes during falsework installation, multiple partial and full closures of the eastbound lanes of the I-210 Freeway will be required. Full eastbound closures will all occur late at night, and the freeway will be reopened by 5:00 a.m. the following mornings.
Also over the next several months, crews will be conducting surveying, geotechnical work and utility locating activities along the planned line. Major construction is scheduled to begin near the end of the year.