Drilling Begins on Gold Line Rail Bridge




Drilling has begun on the foundations for the Gold Line bridge just west of the Santa Anita offramp on the eastbound 210.

According to Gold Line spokesman Habib Balian, Caltrans approved the permit last week and "drilling began yesterday on the first of the three deep foundations. Over the next week, the 11 foot diameter hole for the first foundation (located on the southern shoulder) will be completed,  the reinforcing steel cage will be installed and concrete will be poured and tested. Once drilling is complete on this first foundation, the drill rig and crane will then be moved to the center median of the freeway to start work on the remaining two, 110-foot deep foundations."

- Brad Haugaard