Gold Line 'Substantially' Complete - On Time And On Budget
The Foothill Gold Line from Pasadena to Azusa is now "substantially" complete and will now undergo testing and pre-revenue service. The project, which includes 11.5 miles of light rail, 24 bridges, 14 at-grade rail crossings, six new stations and a 24-acre operations campus, was led by the Foothill Gold Line Construction Authority and was built on time and on budget with an "exceptional safety record thanks to a strong collaboration with Kiewit, Parsons and the corridor cities," said Foothill Gold Line Construction Authority CEO Habib F. Balian.