Progress on Monrovia Rail Maintenance Yard
Gold Line Construction Authority Habib Balian reports that nearly half of the at-grade crossings for the 11.5-mile project are now complete, with six more currently under construction. Also, he writes:
"At the [Monrovia] Operations Campus, crews are nearly ready to start laying the six miles of track that will be installed within the $265 million facility. As of today, more than half of the 213 OCS pole foundations are drilled and poured, and the Maintenance of Way storage structure is nearly complete."
- Brad Haugaard